最是一(yi)年(nian)春好處,發(fa)展奮進(jin)正(zheng)當時(shi)。自春節收假起(qi),承擔著南(nan)寧市以及南(nan)寧經開區各園區重點項目(mu)建設(she)重任的(de)綠港(gang)集團(tuan)(tuan)下屬嘉通(tong)公(gong)司,在(zai)集團(tuan)(tuan)公(gong)司領(ling)導(dao)及嘉通(tong)公(gong)司班子領(ling)導(dao)的(de)帶領(ling)下,奮力扛起(qi)春節后(hou)“復工(gong)復產”大旗(qi),快(kuai)速組織人員施工(gong),并對各重點項(xiang)目進行節后(hou)復工(gong)復產安全(quan)檢查。綠港(gang)·金陽產業(ye)城(cheng)(一(yi)(yi)期(qi))、春吉產業(ye)孵化(hua)園、綠港(gang)·尚尊一(yi)(yi)品等項(xiang)目現場已是機械轟鳴,堅守在項(xiang)目施工(gong)一(yi)(yi)線(xian)的工(gong)人們(men)鉚足干勁,搶施工、趕進度,打響開春生產第一槍,呈現如火如荼施工場景。
綠(lv)港(gang)?金陽產(chan)業(ye)城(一期)項(xiang)目(mu)現場“復工復產開春(chun)忙”
春節后剛剛收假,走進綠港(gang)·金(jin)陽產業城(一期)項目總平施(shi)工的大(da)門口,一陣(zhen)陣(zhen)“吭(hang)隆隆”機械(xie)轟鳴聲劃(hua)破耳(er)際,映入眼(yan)簾(lian)的是鉤機正在緊(jin)張開挖收尾雨污管溝槽(cao),鏟(chan)車正在搬運(yun)清理余土,整個總平項目形成熱火朝天(tian)的復(fu)工復(fu)產壯觀(guan)施(shi)工場(chang)面。
截至2月底,綠港(gang)·金(jin)陽產業城(一期(qi)(qi))總平工(gong)(gong)(gong)程已完成(cheng)擋土墻(qiang)及(ji)圍墻(qiang)、給排(pai)水及(ji)化糞池、道路路基及(ji)碎(sui)石層(ceng)等工(gong)(gong)(gong)作(zuo)項的施(shi)工(gong)(gong)(gong),完成(cheng)項目總量的80%,項目施(shi)工(gong)(gong)(gong)進度(du)達到預期(qi)(qi)效果(guo),預計2023年(nian)3月底完成(cheng)施(shi)工(gong)(gong)(gong),并(bing)通過竣(jun)工(gong)(gong)(gong)驗收交付使用。
“總平項目(mu)是整個項目(mu)配套基礎設施的重要工(gong)(gong)程(cheng)(cheng)之一(yi),項目(mu)快速復工(gong)(gong)復產(chan)(chan)為我們搶(qiang)時間搶(qiang)節點提供工(gong)(gong)期保障,更加堅(jian)定了(le)于3月底(di)攻克完成主體(ti)工(gong)(gong)程(cheng)(cheng)等剩(sheng)余(yu)工(gong)(gong)程(cheng)(cheng)量(liang)的信心。總平工(gong)(gong)程(cheng)(cheng)竣工(gong)(gong)后,將為該(gai)項目(mu)全面竣工(gong)(gong)驗(yan)收奠定良好(hao)基礎,加快項目(mu)如(ru)期交(jiao)付(fu)與(yu)快速投(tou)產(chan)(chan),助力園區企業(ye)生(sheng)產(chan)(chan)經營穩健運行。目(mu)前,該(gai)項目(mu)廠(chang)房(fang)及宿舍(she)樓、飯(fan)堂配套用房(fang)工(gong)(gong)程(cheng)(cheng)正進入室(shi)內裝修(xiu)收尾(wei)階段。”綠港(gang)·金陽產(chan)(chan)業(ye)城(cheng)業(ye)主代(dai)表(biao)甘乃(nai)勝(sheng)如(ru)是說。
綠港·雙創城(cheng)、尚尊一品(二期)項目“復工安檢不放松(song)”
2月中下旬(xun),綠(lv)港集團下屬嘉(jia)通(tong)公司深入綠(lv)港·雙創城、綠(lv)港·尚尊一品(二(er)期)等各在建(jian)項目現場,對復工(gong)復產(chan)、項目進度(du)、安全生產(chan)、現場管理等情(qing)況進行(xing)細致檢查。
在(zai)綠港·雙創城與尚(shang)尊一品(二(er)期(qi))項目現場時,重(zhong)點檢查安全生產、年度施工(gong)(gong)計劃等情(qing)況;著重(zhong)了解(jie)復工(gong)(gong)人員返(fan)崗、施工(gong)(gong)單(dan)位推進(jin)工(gong)(gong)程實施進(jin)度以及(ji)安全質(zhi)量整(zheng)改工(gong)(gong)作。嘉通(tong)公(gong)司(si)要求施工(gong)(gong)單(dan)位及(ji)項目負責人一是要統籌協(xie)調資金問題,保(bao)障項目(mu)復工復產順利進行。二(er)是加快推進施工進度(du),增加人力物(wu)力與(yu)統(tong)籌安排生產資源(yuan),確(que)保項目(mu)如期交付(fu)使(shi)用。三(san)是強化質(zhi)量管控,爭創精品工(gong)程(cheng)、優質(zhi)工(gong)程(cheng)。四是(shi)加強(qiang)安全生(sheng)產,全面(mian)排查(cha)整治安全隱患,堅決杜絕任何安全事故(gu)發生(sheng)。
春節后,嘉通公司迅速從“節日模(mo)式”切換到“工(gong)(gong)作(zuo)模(mo)式”,凝心聚力、提(ti)速(su)爭先,以飽滿的(de)工(gong)(gong)作(zuo)熱情為(wei)開春復工(gong)(gong)后各項工(gong)(gong)作(zuo)開好局。目前各工(gong)(gong)程環節施工(gong)(gong)工(gong)(gong)人已分批(pi)返崗(gang),緊(jin)張有序(xu)地投入到生產建設之中。綠港·尚(shang)尊一品(二期)項目預計(ji)今年4月中旬全(quan)部封頂,目前正(zheng)在對永紅(hong)村派斬坡(po)居民安置進(jin)行選房等工(gong)(gong)作(zuo)宣傳推廣。
春(chun)吉產業孵化(hua)園項(xiang)目“復工進度(du)展新顏”
走進春吉產(chan)業孵化園(yuan),處(chu)處(chu)充滿著生(sheng)機與活力,挖掘機、項目(mu)現(xian)場一(yi)線(xian)施工人(ren)都“各司其(qi)職”,爭先恐后地“擼起袖子(zi)加油干”。一個個熱火朝天蒸(zheng)(zheng)蒸(zheng)(zheng)日(ri)上(shang)的生動場景(jing),正在上(shang)演!
春節過(guo)后(hou),為克服(fu)大多(duo)(duo)數(shu)項目(mu)施工人回鄉過(guo)節尚(shang)未(wei)及時返崗、材(cai)料設(she)(she)備進(jin)場(chang)不(bu)及時困難(nan),綠港(gang)集團下(xia)屬嘉富公(gong)司全力(li)組(zu)織協調,多(duo)(duo)次發(fa)函或約談施工單位全面落實人員、材(cai)料、機械設(she)(she)備進(jin)場(chang)事宜(yi),要(yao)求其采取有效措施加快(kuai)施工進(jin)度。
據(ju)項目(mu)負(fu)責(ze)人介紹,春吉產業孵化園(yuan)包含6棟7層的標準(zhun)(zhun)廠房,總(zong)建筑面積約(yue)為10萬㎡,已(yi)于2022年11月(yue)已(yi)完成外(wai)腳手架的拆(chai)除工作,2022年12月(yue)完成了二層以上的外(wai)墻(qiang)涂(tu)料,裝(zhuang)修(xiu)工作完成約(yue)80%。目前已(yi)有所改(gai)進,室內膩子(zi)、總(zong)平消防管(guan)道、衛(wei)生(sheng)間防水正在施工,橋架已(yi)進場,預計3月(yue)中旬將交付(fu)企業作裝(zhuang)修(xiu)準(zhun)(zhun)備,為園區企業盡快投產運營提供強有力的的場地與(yu)服務支撐。
(嘉通公司 李婷婷、甘乃勝/文)